View CfT Workspace
CfT: Woods Trails for Galway
- Name of Contracting Authority:
- Forbairt Phobail Mhaigh Cuilinn Teo
- Title:
- Woods Trails for Galway
- CfT CA Unique ID:
- Wood Trails
- Evaluation Mechanism:
- Price/Cost Effectiveness
- Description:
- 1.1 This project is for for site clearance along the existing trails, new trail, excavations, breaking of protruding rocks and the construction of walking traills in Killarainey woods. The project shall consist (in summary of): 60mm of 20mm binder course tarmacadam and 25mm of 6mm surface course tarmacadam, laid on 250mm of compacted S.R. 21 Annex E, T.1, complying with I.S. EN 13242:2002+A1:2016, , on a weight stabilising membrane with seal where new surface meets existing surfaces with hot pored bitumen; to extend exsting access road - Approx 10m x 23m Disabled carparking space to comply with Part M of the building regulations 7.2m x 4.8m, complete with paint markings and signage at disabled designated parking space. Class 1 track - 1.8m wide and 399m long with tarmac finish, shown in light blue on the drawings, and will consist of geotextile laid on the existing track, aggregate layer and tarmac layer 5No. 5m diameter wide tarmac circles set on track with furniture and signage as shown on the drawings, on the Class 1 track Class 3 track 2, approx. 600mm wide and 279 meters long with gravel finish, shown in green on the drawings Class 3 track 3, approx. 600mm wide and 86 meters long with gravel finish, shown in yellow on the drawings Class 3 track 4, approx. 600mm wide and 218 meters long with gravel finish, shown in orange on the drawings Class 3 track 5, approx. 600mm wide and 178 meters long with gravel finish, shown in pink on the drawings – note this a new trail to be created through the exsting woodland Class 3 track 6, approx. 600mm wide and 155 meters long with gravel finish, shown in purple on the drawings Class 3 track 7, approx. 600mm wide and 352 meters long with gravel finish, shown in dark blue on the drawings 7No. Benches, 1500 long x 570mm deep with a seat height of 510mm, back height 870mm 24 No. signage bollards 2 No. information boards with an A1 size image of the the trail and relevant information on the trail. Include for ground preparations including removing tree stumps and fallen logs Ground suface on all trails shall be left intact on all trails in order to not to undermine tree growing alongside the track and tree roots. Any necessary clearing of encroaching scrub or overhanging braches shall be carried out using only a saw. Branches may not be broken by machine. Trees not to be removed unless dangerous Steps on trails are required at a number of locations. They shall be constricted of sleepers to form the risers pined into position with compacted hardcore to infill to the thread of each step. Anti-slip GRP sheets 4mm thick to be fixed to sleeper upper surface. Include for forming 30No. steps though the class 3 trails. Exact locations will be agreed on site during the set out of the works.
- Procurement Type:
- Works
- Directive:
- 2014/24/EU (Classic)
- Procedure:
- Open
- CfT Involves:
- A Public Contract
- CPV Codes:
-
45000000-Construction work
45100000-Site preparation work
45112700-Landscaping work
45112711-Landscaping work for parks
45112710-Landscaping work for green areas
- Contact Point:
- Jimmy Keady
- Award per Item:
- No
- Inclusion of e-Auctions :
- No
- NUTS codes:
- IE IE0
- Estimated value (EUR):
- 100,000
- Awarded (CAN) value:
- 120,350
- Above or Below threshold:
- Below
- Time-limit for receipt of tenders or requests to participate:
- 06/10/2023 15:00
- Deadline for dispatching invitations:
- End of clarification period:
- 21/09/2023 15:00
- Tenders Opening Date:
- 06/10/2023 15:30
- Allow suppliers to make an online Expression Of Interest:
- Yes
- Contract awarded in Lots:
- No
- Contract duration in months or years, including any options and renewals:
- 2 months
- Validity of Tender in days or months:
- 180 days
- EU funding:
- No
- Multiple tenders will be accepted:
- No
- Date of Publication/Invitation:
- 01/09/2023 11:14
- TED links for published notices:
-
https://ted.europa.eu/udl?uri=TED:NOTICE:135639-202...
- Date of Awarding:
- 05/03/2024 11:03
- Language of publication:
- EN
- Number of openers:
- One
- Contract Award Date:
- 27/10/2023 15:00
- Date Accepted by Contractor:
- 31/10/2023 15:00